HomeMy WebLinkAboutC2022A013 Fountain Hills Grand - Rosita DrIntergovernmental Agreement
for the
Design, Rights -of --Way Acquisition, Utility Relocations, Construction, Construction
Management and Operation and Maintenance
of the
Grande Blvd. and Rosita Drive Drainage Improvements
between the
Town of Fountain Hills
and the
Flood Control District of Maricopa County
IGA FCD 2022A013
Agenda Item C-l�9 -aa- Oa i -u-off
This Intergovernmental Agreement (this "Agreement") is entered into by and between the Flood
Control District of Maricopa County, a political subdivision of the State of Arizona, acting by and
through its Board of Directors (the "DISTRICT'), and the Town of Fountain Hills, a municipal
corporation, acting by and through its Mayor and Town Council, (the "TOWN'). The Town and
the District are collectively referred to as the PROJECT PARTNERS and as a PROJECT
PARTNER.
This Agreement shall become effective as of the date it has been executed by all PROJECT
PARTNERS.
STATUTORY AUTHORIZATION
1. The DISTRICT is empowered by Arizona Revised Statutes (A.R.S.) § 48-3603, as revised, to
enter into this Agreement and has authorized the undersigned to execute this Agreement on
behalf of the DISTRICT.
2. The TOWN is empowered by A.R.S. § 9-240(B) and A.R.S. §11-952, as amended, to enter into
this Agreement and has authorized the undersigned to execute this Agreement on behalf of the
TOWN.
BACKGROUND
3. On October 19, 2022 the Board of Directors of the DISTRICT (the Board) adopted Resolution
FCD 2022R003 (C-69-23-009-X-00) authorizing the DISTRICT to cost -share in projects
recommended under the DISTRICT Small Project Assistance Program.
4. Under the DISTRICT'S Small Project Assistance Program fox Fiscal Year 2023, the TOWN
proposed the Grande Blvd. and Rosita Drive Drainage Improvements (the "PROJECT") to
provide the following benefits:
IGA FCD 2022A013 PCN 699.23.35
4,I Reduce the flood hazard to a property that has experienced historic flooding.
5. The PROJECT has Ueen recommended by DISTRICT staff for he Fiscal Yeat 2023 program.
PURPOSE OF THE AGREEMENT
6. The purpose of this tlgteement is to identify and define the responsibilities of the DISTRICT
and the TOWN for the design, rights -of -way acquisition, utility relocations, construction,
construction management, and operation and maintenance of the PROJECT.
TERMSOFAGREEMENT
7. The PROJECT shall mean the features required to accomplish the benefits enumerated in
paragraph 4 of this Agreement. Features of the PROJECT, as envisioned at the time of this
Agreement, are represented in Exhibit A but are subject to change without amendment to this
Agreement.
8. PROJECT
DESIGN AND CONSTRUCTION COST
shall mean the actual amount of money
required to
complete the
flood control features of the
PROJECT that are completed and
invoiced by
the TOWN to
the DISTRICT between July
1, 2022 and June 30, 2024,
8.1 The following costs axe expressly excluded from the PROJECT DESIGN AND
CONSTRUCTION COST shared under this Agreement:
8.1.1 Costs associated with rights -of --way acquisition, permitting, construction
management (including materials testing and survey work), operations and
maintenance.
8.1.2 Costs associated with multi -use, landscaping or aesthetic features.
8.1.3 Costs associated with utility conflicts and utility relocations.
8.2 The
PROJECT
DESIGN AND CONSTRUCTION COST is
estimated to be $290,000,
but
is subject to
change without amendment to this Agreement.
9. The DISTRICT shall:
9.1 Fund seventy-five percent (75%) of the PROJECT DESIGN AND CONSTRUCTION
COST incurred and invoiced behvicen July 1, 2022 and June 30, 2024, with the funding
from the DISTRICT limited to a maximum of $1,000,000 in accordance with the
DISTRICT's Small Project Assistance Program. The DISTRICT's current estimated
funding share is $217,500, DISTRICT funds will be from the DISTRICT's secondary tax
levy revenues and DISTRICT funding shall be contingent upon the availability of
DISTRICT Capital Improvement Program Budget funding. This term shall not be
amended.
9.2 Reimburse the TOWN per the terms of this Agreement within thirty (30) days of receipt
of an invoice from the TOWN fox its share of the PROJECT DESIGN AND
CONSTRUCTION COST.
IGA TCD 2022A013 PCN 699.23.35 PAGE 2 OF 9
9.3
Participate m a final inspection of the completed PROJECT with the M N.
10. The
TOWN shall:
10.1
Fund the full PROJECT DESIGN AND CONSTRUCTION COSTS not reimbursed by
the DISTRICT, making the TOWN's estimated PROJECT DESIGN AND
CONSTRUCTION COST share $72,500 and TOWN will fully fund all PROJECT costs
for any work completed and invoiced before July 1, 2022 or after June 30, 2024.
10.2
Fully and solely pay any payment required that does not fall within the definition of
PROJECT DESIGN OR CONSTRUCTION COST.
10.3
Serve as the lead agency for all aspects of PROJECT implementation.
10.4
Invoice the DISTRICT as follows:
10.4.1 Within thirty (30) days of award of a PROJECT' construction contract for one-half
(1 /2) of its share of the PROJECT DESIGN AND CONSTRUCTION COSTS.
10.4.2 Within thirty (30) days of completion of construction of the PROJECT, but no later
than June 30, 2024, prepare a final accounting including change order costs not
previously paid, and invoice the DISTRICT for the remainder of its share of the
PROJECT DESIGN AND CONSTRUCTION COST incurred, if any, to date.
10.5 Reunburse the DISTRICT for any previous over-pa}ments.
10.6 Design the PROJECT, provide PROJECT plans and specifications to the DISTRICT
(including interim submittals as appropriate) for review and comment. The DISTRICT
shall provide, within three (3) weeks of receipt of the plans and specifications from the
TOWN, comments on the plans and specifications, if any. The TOWN shall incorporate
the comments provided by the DISTRICT into the PROJECT as appropriate.
10.7 Coordinate and staff any necessary public involvement activities related to the PROJECT.
10.8 Obtain all permits required for the PROJECT.
10.9 Obtain rights -of -way required for the PROJECT.
10.10 Relocate conflicting utilities.
10.11 Construct the PROJECT, provide construction management (including materials testing
and survey work), and provide any proposed construction change orders to the
DISTRICT for concurrence.
10.12 Coordinate a final inspection of the completed PROJECT with the DISTRICT.
10.13 Own the completed PROJECT and be responsible for operation and maintenance of the
completed PROJECT. The maintenance activities to be performed include, but are not
limited to, maintaining the flood control function of the PROJECT, including sediment
and vegetation removal and any and all aesthetic, park, and public use features,
maintenance of landscaping, irrigation, multi -use trails and berms, removal of trash and
debris, electricity and other operation costs for the facilities, vandalism repair and
IGA PCD 2022A013 PCN 69A23.35 PAGE 3 OP 9
eplacement, and structural repair and replacement of the flood control structures. The
TOWN may delegate this responsibility to a third party but will remain ultimately
accountable to the DISTRICT under this Agreement.
10.14 On an annual basis, commencing on the First an versary date of he complet on and
acceptance of the project, provide written notification to the DISTRICT that the project
has been properly maintained by the TOWN over the past year in accordance with the
project design intent and to ensure proper hydraulic function.
10.15 Require that any contractor selected fox the PROJECT:
10.15.1 Warrant
its compliance with all federal immigration
laws
and regulations that
relate to
its employees and their compliance with A.R.S.
§ 23-214(A);
10.15.2 Agree that a breach of the warranty under paragraph 10.15.1 shall be deemed a
material breach of contract and is subject to penalties up to and including
termination of the contract;
10.15.3 Agree that the DISTRICT retains the legal right to inspect the papers of the
contractor or subcontractor employee(s) who work(s) on this Agreement to
ensure that contractor or subcontractor is complying with the warranty under
paragraph 10.15.1;
10.16 Warrants and certifies that it does not cuxxendy, and agrees fox the duxadon of the contract
that it will not, use:
10.16.1 The forced labor of ethnic Uyghuxs in the People's Republic of China.
10.16.2 Any goods or services produced by the forced labor of ethnic Uyghurs in the
People's Republic of China.
10.16.3 Any contractors, subcontractors or suppliers that use the forced labor or any
goods or services produced by the forced labor of ethnic Uyghuxs in the People's
Republic of China.
If Town becomes aware during the term of the Agreement that any Contractor is not in
comphance with this paragraph, the Town shall notify the County within five business
days after becoming aware of the noncompliance. Failure of Town to provide a written
certification that the appropriate contractor has remedied the noncompliance within one
hundred eighty (180) days after notifying the public entity of its noncompliance, thus
Agreement shall terminate unless the Term of this Agreement shall end prior to said one
hundred eighty (180) day period.
11. Any
local permits
required
for
the PROJECT that
are issued by
either PROJECT PARTNER
shall
be issued at no
cost to
the
PROJECT.
12. Either PROJECT PARTNER may, with mutual written agreement of all PROJECT
PARTNERS, delegate responsibilities to another party. Any delegation, however, shall not
relieve the delegating PROJECT PARTNER of its original responsibilities as defined herein.
13. Each PROJECT PARTNER certifies that it has disclosed to the other PROJECT PARTNER
any lmown ongoing ox anticipated litigation (to which it is a party) related to the PROJECT or
IGA PCD 2022A013 PCN 699.23.35 PAGE 4 GP 9
PROJECT -affiliated
flooding
hazards,
and shall continue to make such disclosures through the
duration of
this Agreement.
14. In the case of any d spute over any items n this Agreement, the PROJECT PARTNERS agree
to use their best efforts and enter into good faith negotiations to resolve the disputed matters.
However, this shall not limit the rights of the PROJECT PARTNERS to seek any remedies
provided by law.
15. Each PROJECT PARTNER shall take reasonable and necessary actions within its authority to
ensure that only storm water is discharged into the PROJECT, and that such discharges into the
PROJECT comply at the point of discharge with any applicable requirements of the U.S.
Environmental Protection Agency, Clean Water Act, Arizona Pollutant Discharge Elimination
System or any other applicable discharge requirements, including any permit requirements.
16. The PROJECT PARTNERS agree to equally share the cost of a PROJECT compliance and cost
audit to be initiated within sixty (60) days of PROJECT completion, if requested by either
PROJECT PARTNER. An independent auditing firm on contract to the DISTRICT and
agreeable to the PROJECT PARTNERS will perform the audit. Any payments or
reimbursements necessary to bring the PROJECT into compliance with the audit findings shall
be made within 45 days of acceptance by all PROJECT PARTNERS of the audit report.
17. Each PROJECT PARTNER (indemnitor) shall, to the extent permissible by law, indemnify,
defend and save harmless the others (indemn tees) including agents, officers, directors, governors
and employees thereof, from and against any loss or expense incurred as a result of any claim or
suit of any nature whatsoever, which arises out of indemnitor's negligent or wrongful acts or
omissions pursuant to this Agreement. The TOWN shall further, to the extent permissible by
law, indemnify, defend and save harmless the DISTRICT including agents, officers, directors,
governors and employees thereof, from and against any loss or expense incurred as a result of
any claim or suit of any nature whatsoever, which arises out of recreational use of the PROJECT
in the event that it elects to invite such use (with or without DISTRICI" concurrence). Such
indemnification obligations shall encompass any personal injury, death or property damages
resulting from the indemnitor's negligent or wrongful acts or omissions, as well as reasonable
attorney fees, court costs, and other expenses relating to the defense against claims or litigation,
incurred by the indemnitee. Indemnitee shall be liable for its own negligence or wrongful acts as
provided by law.
18. Each PROJECT PARTNER
18.1 Shall comply with A.R.S. §§ 41-4401 and 23-214(A). Failure by either PROJECT
PARTNER to comply with A.R.S. §§ 41-4401 and 23-214(A) shall be deemed a breach of
this Agreement and is subject to penalties up to and including termination of the
Agreement.
18.2 Retains the legal sight to inspect the records of the other PROJECT PARTNER's and any
contractors' ox subcontractors' employees performing work under this Agreement to
verify compliance with A.R.S. §§ 41-4401 and 23-214(A).
19. All notices
or demands upon
any PROJECT
PARTNER shall be
in writing and shall be
delivered in
person, by express
delivery service
fox which a receipt is
obtained ox sent by mail
addressed as
follows:
IGA PCD 2022A013 PCN 69223.35 PAGE 5 OP 9
Flood Control District of 1Viancopa County Town of Fountain Hills
Director Town Engineer
2801 West Durango Street 16705 E. Ave. of the Fountains
Phoenix, Arizona 85009-6399 Fountain Hills, AZ 85268
20. Thus Agreement shall expire either (a) hvo years from the date o£ execution Uy all PROJECT
PARTNERS, or (b) upon both completion of the PROJECT and satisfaction of all funding
obligations and reimbursements associated wide this Agreement, whichever is the first to occur.
However, by mutual written agreement of all PROJECT PARTNERS, this Agreement may be
amended or terminated except as expressly stated in this Agreement. The operation and
maintenance and indemnification provisions of this Agreement shall survive the expiration of
this Agreement.
21. This tgreement is subject to the provisions of tLR.S. § 38-511.
22. Attached to thus Agreement ox contained herein axe the written determinations by the
appropriate attorneys for the PROJECT PARTNERS, that these agencies are authorized under
the laws of the State of Arizona to enter into this Agreement and that it is in proper form.
23. If legislation is enacted after the effective date
of thus Agreement that changes the
relationship ox
structure of one
or more PROJECT PARTNERS, the PROJECT PARTNERS
agree that this
Agreement shall
be renegotiated at the written
request of either PROJECT PARTNER.
IGA L'CD 2022A013 PCN 699.23.35 PAGC 6 OP 9
DocuSign Envelope ID: A0269Al2-9177-4424-98CC-998C8BOD589F
C 1�1&40021-X' 00
FLOOD CONTROL DISTRICT OF MARICOPA COUNTY
A Political Subdivision of the State of Arizona
Recommended by:
[oocusi¢nea ny
V. 11/1/2022
sion ocn�esanec...
Michael A. Fulton Date
Director
Approved and Accepted:
By: - 4F)� &yPop< OV 1 6 2022
Chairman, Board of Directors Date
Attest:
DOUG Date
The foregoing Intergovernmental Agreement FCD 2022A013 has been reviewed pursuant to A.R.S.
Section 11-952, as amended, by the undersigned General Counsel, who has determined that it is in
proper form and within the powers and authority granted to the Flood Control District of Maxicopa
County under the laws of the State of Arizona.
[oocusignea by:
� tn.l, p� 11/1/zozz
9 9otoDB524D1
General Counsel Date
IGA FCD 2022A013 PCN 699.23.35 PAGC 7 OF 9
TOWN OF FOUNTAIN HILLS
A Municipal Corporation
Approved and ticcepted By:
C7%/� 10/25/2022
Giany Dice (Oct 2520 08:55 PDT)
Ginny Dickey, Mayor Date
By:
Attest:
.L�+udm%YL¢+s� /rake 10/25/2022
Linda Mendenhall, Town Clerk Date
The foregoing Intergovexntnental Agreement F'CD 2022A013 has been reviewed pursuant to A.R.S.
Section 11-952, as amended, by the undersigned attorney who has determined that it is in proper
form and within the power and authority granted to the Town of Carefree under the laws of the State
of Arizona.
Aaron AYnson (Oct 25 2022 08'32 PDT)
Town Attorney Date
IGA FCD 2022A013 PCN 699.23.35 PAGE 8 OF 9
Exhibit A: Grande Blvd. and Rosita Drive Drainage Improvements
Grand Blvd. and Ros0a Drive Drainage Improvements NOI IO SC3iC
N
A
IGA PCD 2022A013 PCN 699.23.35 PAGE 9 OP 9
IGA-Grande Blvd.osit r_
Final Audit Report 2022-10-25
Created 2022-10-25
By:Robert Durham (rdurham@fountainhillsaz.gov)
Status: :Signed
Transaction ID: CBJCHBCAABAAMA9xHRTFZyfnDaE5tMc1mh7lwnPrNs9n
"IGA-Grande Blvd. Rosita Dr_" History
,�
Document
created by Robert Durham (rdurham@fountainhillsaz.gov)
2022-10-25 -
3:27:30 PM GMT- IP address: 184.178.192.162
t=`'�
Document
emailed to Beata
Bogdan
(bbogdan@fountainhillsaz.gov)
for approval
2022-10-25 -
3:30:14 PM GMT
�
Email viewed by
Beata Bogdan (bbogdan@fountainhillsaz.gov)
2022-10-25 - 3:30:24
PM GMT- IP address: 184,178,192.162
t3o
Document approved by Beata
Bogdan
(bbogdan@fountainhillsaz.gov)
Approval Date: 2022-10-25 - 3:30:44
PM GMT -
Time Source: server- IP address:
184.178.192.162
C`o-
Document
emailed to Aaron
Arnson (aaron@piercecoleman.com)
for signature
2022-10-25 -
3:30:46 PM GMT
r�
Email viewed by
Aaron Arnson (aaron@piercecoleman.com)
2022-10-25 - 3:32:18
PM GMT- IP address: 69.53.213.227
bo Document e-signed by Aaron Arnson (aaron@piercecoleman.com)
Signature Date: 2022-10-25 - 3:32:27 PM GMT - Time Source: server- IP address: 69.53.213.227
Cw
5
Document
emailed to gdickey@fountainhillsaz.gov
for
signature
2022-10-25 -
3:32:28 PM GMT
Email viewed by gdickey@fountainhillsaz.gov
2022-10-25 - 3:54:20 PM GMT- IP address: 68.2.112.40
do
Signer gdickey@fountainhillsaz.gov entered name
at signing
as Ginny
Dickey
2022-10-25 - 3:55:41 PM GMT- IP address: fi8.2.112.40
do Document e-signed by Ginny Dickey (gdickey@fountainhillsaz.gov)
Signature Date: 2022-10-25 - 3:55:43 PM GMT -Time Source: server- IP address: 68.2.112.40
.�+Adobe
Acrobat Sigr1
Lw Document emailed to Linda Mendenhall (Imendenhall@fountainhillsaz.gov) for signature
2022- 10-25 - 3:55:44 PM GMT
mo Email viewed by Linda Mendenhall (Imendenhall@fountainhillsaz.gov)
2022-10-25 - 3:58:41 PM GMT- IP address: 184.178.192.162
CYo Document e-signed by Linda Mendenhall (Imendenhall@fountainhillsaz.gov)
Signature Date: 2022-10-25 - 3:58:56 PM GMT - Time Source: server- IP address: 184,178,192.162
Agreement completed.
2022-10-25 - 3:58:56 PM GMT
} �.,, Powered by
++ Adobe
Acrobat Sign