HomeMy WebLinkAboutC2022A014 Fountain Hills Villa-Deuce CtIntergovernmental Agreement
for the
Design, Rights -of -Way Acquisition, Utility Relocations, Construction, Construction
Management and Operation and Maintenance
of the
Courtside Villa -Deuce Ct, and Parcel F: Drainage Improvements
between the
Town of Fountain Hills
and the
Flood Control District of Maricopa County
IGA FCD 2022A014
Agenda Item C.-ioS,d3-O?o-y-Od
This Intexgoverntnental Agreement (this "Agreement") is entered into by and between the Flood
Control District of Maricopa County, a political subdivision of the State of Arizona, acting by and
through its Board of Directors (the "DISTRICT'), and the Town of Fountain Hills, a municipal
corporation, acting by and through its Mayor and Town Council, (the "TOWN"). The Town and
the District are collectively referred to as the PROJECT PARTNERS and as a PROJECT
PARTNER.
This Agreement shall become effective as of the date it has been executed by all PROJECT
PARTNERS.
STATUTORY AUTHORIZATION
1. The DISTRICT is empowered by Arizona Revised Statutes (A.R.S.) § 48-3603, as revised, to
enter into this Agreement and has authorized the undersigned to execute this Agreement on
behalf of the DISTRICT.
2. The TOWN is empowered by A.R.S. § 9-240(B) and A.R.S. §l 1-952, as amended, to enter into
this Agreement and has authorized the undersigned to execute this Agreement on behalf of the
TOWN.
BACKGROUND
3. On October 19, 2022 the Board of Directors of the DISTRICT (the Boazd) adopted Resolution
FCD 2022R003 (C-69-23-009-X-00) authorizing the DISTRICP to cost -share in projects
recommended under the DISTRICT's Small Project Assistance Program,
4. Under the DISTRICT'S Small Project Assistance Program for Fiscal Year 2023, the TOWN
proposeA the Courtside Villa -Deuce Ct. and Parcel F: Drainage Improvements (the
"PROJECT' to provide the following benefits:
IGA FCD 2022A014 PCN 699.23.36 PAGE 1 OF 9
4.1 Reduce the flood hazard to a property that has experienced historic flooding.
5. The PROJECT has been recommended by DISTRICT staff for he Fiscal Yeat 2023 program.
PURPOSE OF THE AGREEMENT
6. The purpose of this Agreement is to identify and define the responsibilities of the DISTRICT
and the TOWN for the design, rights -of -way acquisition, utility relocations, construction,
construction management, and operation and maintenance of the PROJECT.
TERMS OP AGREEMENT
7. The PROJECT shall mean the features required to accomplish the benefits enumerated in
paragraph 4 of this Agreement. Features of the PROJECT, as envisioned at the time of this
Agreement, are represented in Exhibit A but are subject to change without amendment to this
Agreement.
8. PROJECT DESIGN AND CONSTRUCTION COST shall mean the actual amount of money
required to complete the flood control features of the PROJECT that are completed and
invoiced by the TOWN to the DISTRICT between July 1, 2022 and June 30, 2024.
8.1 The following costs are expressly excluded from the PROJECT DESIGN AND
CONSTRUCTION COST shared under this Agreement:
8.1.1 Costs associated with rights -of --way acquisition, permitting, construction
management (nclud ng materials tes ng and survey work), opera t ons and
maintenance.
8.1.2 Costs associated with multi -use, landscaping ox aesthetic features.
8.1.3 Costs associated with utility conflicts and utility relocations.
8.2 The PROJECT DESIGN AND CONSTRUCTION COST is estimated to be $95,000,
but is subject to change without amendment to this Agreement.
9. The DISTRICT shall:
9.1 Fund seventy -Five percent (75%) of the PROJECT DESIGN AND CONSTRUCTION
COST incurred and invoiced between July 1, 2022 and June 3Q, 2024, with the funding
from the DISTRICT limited to a maximum of $1,000,000 in accordance with the
DISTRICT's Small Project Assistance Program. The DISTRICT's current estimated
funding share is $71,250. DISTRICT funds will be from the DISTRICT's secondary tax
levy revenues and DISTRICT funding shall be contingent upon the availability of
DISTRICT Capital Improvement Program Budget funding. This term shall not be
amended.
9.2 Reimburse the TOWN per the terms of this Agreement within thirty (30) days of receipt
of an invoice from the TOWN fox its share of the PROJECT DESIGN AND
CONSTRUCTION COST.
RCD 2022A014 PCN 699.23.36 PAGE 2 OP 9
PROJECT -affiliated flooding hazards, and shall continue to make such disclosures through the
duration of this Agreement.
14. In the case of any dispute over any items in this Agreement, the PROJECT PARTNERS agree
to use their best efforts and enter into good faith negotiations to resolve the disputed matters.
However, this shall not limit the rights of the PROJECT PARTNERS to seek any remedies
provided by law.
15. Each PROJECT PARTNER shall take reasonable and necessary actions within its authority to
ensure that only storm water is discharged into the PROJECT, and that such discharges into the
PROJECT comply at the point of discharge with any applicable requirements of the U.S.
Environmental Protection Agency, Clean Water Act, Arizona Pollutant Discharge Elimination
System or any other applicable discharge requirements, including any permit requirements.
16. The PROJECT PARTNERS agree to equally share the cost of a PROJECT compliance and cost
audit to be initiated within sixty (60) days of PROJECT completion, if requested by either
PROJECT PARTNER. An independent auditing firm on contract to the DISTRICT and
agreeable to the PROJECT PARTNERS will perform the audit. Any payments or
reimbursements necessary to bring the PROJECT into compliance with the audit findings shall
be made within 45 days of acceptance by all PROJECT PARTNERS of the audit report.
17. Each PROJECT PARTNER (indemnitox) shall, to the extent permissible by law, indemnify,
defend and save harmless the others (indemnitees) including agents, officers, directors, governors
and employees thereof, from and against any loss or expense incurred as a result of any claim or
suit of any nature whatsoever, which arises out of indemnitor's negligent or wrongful acts or
omissions pursuant to this Agreement. The TOWN shall further, to the extent permissible by
law, indemnify, defend and save harmless the DISTRICT including agents, officers, directors,
governors and employees thereof, from and against any loss or expense incurred as a result of
any claim or suit of any nature whatsoever, which arises out of recreational use of the PROJECT
in the event that it elects to invite such use (with or without DISTRICT concurrence). Such
indemnification obligations shall encompass any personal injury, death or property damages
resulting from the indemnitor's negligent or wrongful acts or omissions, as well as reasonable
attorney fees, court costs, and other expenses relating to the defense against claims or litigation,
incurred by the indemnitee. Indemnitee shall be liable for its own negligence or wrongful acts as
provided by law.
18. Each PROJECT PARTNER
18.1 Shall comply with A.R.S. §§ 41-4401 and 23-214(A). Failure by either PROJECT
PARTNER to comply with A.R.S. §§ 41-4401 and 23-214(A) shall be deemed a breach of
this Agreement and is subject to penalties up to and including termination of the
Agreement.
18.2 Retains the legal right to inspect the records of the other PROJECT PARTNER's and any
contractors' or subcontractors' employees performing work under this Agreement to
verify compliance with A.R.S. §§ 41-4401 and 23-214(A).
19. All notices or demands upon any PROJECT PARTNER shall be in writing and shall be
delivered in person, by express delivery service for which a receipt is obtained or sent by mail
addressed as follows:
IGA PCD 2022A014 PCN G99.23.36 PAGE 5 OP 9
Flood Control District of Mancopa County Town of Fountain Hills
Director Town Engineer
2801 West Durango Street 16705 E. Ave. of the Fountains
Phoenix, Arizona 85009-6399 Fountain Hills, AZ 85268
20. Tlus Agreement shall exp e ei he (a) two years from the date of execut on by all PROJECT
PARTNERS, or (b) upon both completion of the PROJECT and satisfaction of all funding
obligations and reimbursements associated with this Agreement, whichever is the first to occur.
However, by mutual written agreement of all PROJECT PARTNERS, this Agreement may be
amended or terminated except as expressly stated in this Agreement. The operation and
maintenance and indemnification provisions of this Agreement shall survive the expiration of
this Agreement.
21. This Agreement is subject to the provisions of A.R.S. § 38-511
22. Attached to this Agreement or contained herein are the written determinations by the
appropriate attorneys for the PROJECT PARTNERS, that these agencies are authorized under
the laws of the State of Arizona to enter into this Agreement and that it is in proper form.
23. If legislation is enacted after the effective date of this Agreement that changes the relationship ox
structure of one or more PROJECT PARTNERS, the PROJECT PARTNERS agree that this
Agreement shall be renegotiated at the written request of either PROJECT PARTNER.
IGA RCD 2022A014 PCN 699.23.3b PAGE G OR 9
C-to9=i3-ozo-x -oo
DocuSign Envelope ID: A0269Al2-9177-4424-98CC-998C8BOD589F
FLOOD CONTROL DISTRICT OF MARICOPA COUNTY
A Political Subdivision of the State of Arizona
Recommended by:
C000�siy�ea ny:
�Lf(J�ALI�tlbN 11/1/2022
Michael A. Fulton Date
Dixectox
Approved and Accepted:
By: PLXk/ &'L-- NOV 1 6 2022
Chairman, Board of Directors Date
Attest:
VA"NOWNER 1A AN 1 6 2022
oaJ Date
The foregoing Intergovernmental Agreement FCD 2022A014 has been reviewed pux�uant to A.R.S.
Section 11-9522 as amended, by the undersigned General Counsel, who has determined that it is in
proper form and within the powers and authority granted to the Flood Control District of Maxicopa
County under the laws of the State of Arizona.
Coocusigoeapny:
� f � 11/1/2022
exEaeotooe524o1...
General Counsel Date
IGA FCD 2022A014 PCN 699.23.36 PAGE 7 OF 9
TOWN OF FOUNTAIN HILLS
A Municipal Corporation
Approved and Accepted BI
Fin
GY6r bu keL/ 10/28/2022
0 Nc ce (D 28, 2 2209:13 PDT)
Ginny Dickey, Mayor Date
By:
Attest:
�w il2wse/a�s/e¢� 10/28/2022
Linda Mendenhall, Town Clerk Date
The foregoing Intergovernmental Agreement FCD 2022A014 has been reviewed pursuant to A.R.S.
Section 11-952, as amended, by the undersigned attorney who has determined that it is in proper
form and within the power and authority granted to the Town of Carefree under the laws of the State
of Arizona.
��- 10/28/2022
Aaron Amson (Oct 28, 2022 08:52 PDT)
Town Attorney Date
IGA RCD 2022A014 PCN 699.23.36 PAGTi, 8
Exhibit A: Courtside villa -Deuce Ct. and Parcel P: Drainage Improvements
Not to Scale
Cou rtside Villa -Deuce Ct. and Parcel F: Drainage Improvements nJ
A
IGA PCD 2022A014 PCN 699.23.36 PAG); 9 OP 9
IGA2022AO1=CourtsIde Vllla®Deuce Ct
Final Audit Report 2022-10-28
Created: 2022-10-25
By: Robert Durham (rdurham@founlainhilisaz.gov)
Status: Signed
Transaction ID: CBJCHBCAABAACIdHgtsTJh-Hq-HCgaVJh14f15axW-ru
"IGA2022A01-Courtside Villa -Deuce Ct_" History
5 Document created by Robert Durham (rdurham@fountainhillsaz.gov)
2022-10-25 - 3:31:02 PM GMT- IP address: 184,178,192,162
24 Document emailed to Beata Bogdan (bbogdan@fountainhilisaz.gov) for approval
2022-10-25 - 3:34:28 PM GMT
Email viewed by Beata Bogdan (bbogdan@fountainhillsaz.gov)
2022-10-25 - 3:34:39 PM GMT- IP address: 184.178.192.162
650 Document approved by Beata Bogdan (bbogdan@fountainhillsaz.gov)
Approval Date: 2022-10-25 - 3:35:06 PM GMT - Time Source: server- IP address: 184,178,192.162
Document emailed to Aaron Arnson (aaron@piercecoleman.com) for signature
2022-10-25 - 3:35:07 PM GMT
Email viewed by Aaron Arnson (aaron@piercecoleman.com)
2022-10-25 - 11:49:50 PM GMT- IP address: 104.28.111.174
Email viewed by Aaron Arnson (aaron@piercecoleman.com)
2022-10-28 - 3:51:54 PM GMT- IP address: 174.76.46.68
too Document e-signed by Aaron Arnson (aaron@piercecoleman.com)
Signature Date: 2022-10-28 - 3:52:06 PM GMT - Time Source: server- IP address: 174.76.46.68
P4 Document emailed to gdickey@fountainhillsaz.gov for signature
2022-10-28 - 3:52:08 PM GMT
Email viewed by gdickey@fountainhillsaz.gov
2022-10-28 - 4:12:48 PM GMT- IP address: 68.2.112,40
40 Signer gdickey@fountainhillsaz.gov entered name at signing as Ginny Dickey
2022-10-28 - 4:13:10 PM GMT- IP address: 68.2.112.40
Powered by
��.► Adobe
Acrobat Sign
&5p Document e-signed by Ginny Dickey (gdickey@fountainhillsaz.gov)
Signature Date: 2022-10-28 - 4:13:12 PM GMT - Time Source: server- IP address: 68.2.112.40
04 Document emailed to Linda Mendenhall (Imendenhall@fountainhilisaz.gov) for signature
2022-10-28 - 4:13:13 PM GMT
Email viewed by Linda Mendenhall (Imendenhall@fountainhillsaz.gov)
2022-10-28 - 4:18:59 PM GMT- IP address: 98.177.118.140
CSC Document e-signed by Linda Mendenhall (Imendenhall@fountainhilisaz.gov)
Signature Date: 2022-10-28 - 4:19A3 PM GMT -Time Source: server- IP address: 98.177.118.140
Agreement completed.
2022-10-28 - 4:19:13 PM GMT
F .., Powered by
Adobe
Acrobat Sign