NOTICE OF MEETING
SPECIAL WORK SESSION
FOUNTAIN HILLS TOWN COUNCIL
Mayor Gerry M. Friedel
Vice Mayor Hannah Toth
Councilmember Gayle Earle
Councilmember Brenda Kaliviankis
Councilmember Rick Watts
Councilmember Peggy McMahon
Councilmember Allen Skillicorn
TIME:1:00 P.M. – SPECIAL WORK SESSION (CAPITAL IMPROVEMENT PROJECTS)
WHEN:TUESDAY, MARCH 25, 2025
WHERE:FOUNTAIN HILLS COUNCIL CHAMBERS
16705 E. AVENUE OF THE FOUNTAINS, FOUNTAIN HILLS, AZ
Councilmembers of the Town of Fountain Hills will attend either in person or by telephone conference call; a quorum of the Town’s various
Commission, Committee or Board members may be in attendance at the Council meeting.
Notice is hereby given that pursuant to A.R.S. §1-602.A.9, subject to certain specified statutory exceptions, parents have a right to consent
before the State or any of its political subdivisions make a video or audio recording of a minor child. Meetings of the Town Council are audio
and/or video recorded and, as a result, proceedings in which children are present may be subject to such recording. Parents, in order to
exercise their rights may either file written consent with the Town Clerk to such recording, or take personal action to ensure that their child
or children are not present when a recording may be made. If a child is present at the time a recording is made, the Town will assume that
the rights afforded parents pursuant to A.R.S. §1-602.A.9 have been waived.
AGENDA
1.CALL TO ORDER – Mayor Gerry M. Friedel
2.ROLL CALL – Mayor Gerry M. Friedel
3.REGULAR AGENDA
A.CONSIDERATION AND DIRECTION: Directing staff to proceed with the Council's selected FY 26
Capital Improvement Projects.
4.ADJOURNMENT
Dated this _____ day of __________, 2025.
______________________________________
Angela Padgett-Espiritu, Acting Town Clerk
The Town of Fountain Hills endeavors to make all public meetings accessible to persons with disabilities. Please call
480-816-5100 (voice) or 1-800-367-8939 (TDD) 48 hours prior to the meeting to request a reasonable
accommodation to participate in the meeting or to obtain agenda information in large print format. Supporting
documentation and staff reports furnished the Council with this agenda are available for review in the Clerk's
Office.
Town Council Work Session of March 25, 2025 2 of 2
ITEM 3. A.
TOWN OF FOUNTAIN HILLS
STAFF REPORT
Meeting Date: 03/25/2025 Meeting Type: Town Council CIP Work Session
Agenda Type: Council Discussion Submitting Department: Public Works
Prepared by: Justin Weldy, Public Works Director
Staff Contact Information: Justin Weldy, Public Works Director
Request to Town Council CIP Work Session (Agenda Language): CONSIDERATION AND DIRECTION: Directing
staff to proceed with the Council's selected FY 26 Capital Improvement Projects.
Staff Summary (Background):
Staff will present a preview of several Capital Improvement Projects that will have high community visibility and
address areas of public concern.
Community Services FY 2026 Proposed Capital Projects:
Centennial Pavilion Shade Structure Lighting:
Adding dark sky-compliant lighting to the Centennial Pavilion shade structure to help enhance the nighttime
useability for evening events and activities in the area next to the Dark Sky Discovery Center.
Avenue Linear Park: Multi-Year
This is a three-year improvement project which is in year two of three and will include completing the shade
structure installation, adding new event power outlets and adding colored lighting to the fountains.
Desert Vista: Multi Year
Pump building structure to protect the irrigation pump, controller and electrical from damage from exposure to
the elements and irrigation leaks. It will also enable the addition of an injection system to help improve water
quality for the turf and plants.
Desert Vista Dog Park Renovations:
The project will provide enhancements to the dog splash pad area, tree replacement, turf improvement and
signage improvement.
Fountain Park Splash Pad Shade Electrical and Lighting:
The Splash pad picnic shade area has been a success and adding lighting for nighttime usage will continue to
improve the area for evening usage and events and gatherings held after dark.
Fountain Park Ramadas: Multi-Year
After looking into multiple repair options, it has been determined that it will be more cost-effective to do a total
replacement. They were installed in 2000 and are structurally failing. The plan is to replace three of the five
ramadas this fiscal year.
ramadas this fiscal year.
Fountain Park Panorama Hillside Erosion Control:
The Panorama hillside erosion control project is scheduled to lessen the slope of the hill and landscape to help
prevent run-off onto the sidewalk. This project was approved in FY24 but was not completed due to time
constraints.
Four Peaks Electrical Building: Multi-Year
The small electrical room next to the new restroom is not large enough for the electrical equipment that it
houses. This CIP will add a new building using an existing slab to house the electrical components as well as
provide extra storage.
Pleasantville Park: Multi-Year- Development Fees
This new pocket park is scheduled for construction in FY26. It will provide our first designated star-gazing
location in town as well as a great location for daytime classes and educational experiences as well as
landscaping garden to showcase plants capable of being grown in Fountain Hills.
Golden Eagle Playground: Multi-Year
Staff is requesting $50,000 in carry-over if not completed in FY25
Public Works FY 2026 Proposed Capital Projects:
Palomino Boulevard Reconstruction: Multi-Year
This project involves the full-depth removal and replacement of the existing asphalt pavement on Palomino
Boulevard. The current pavement has exceeded its useful life, necessitating complete reconstruction to ensure
long-term roadway performance and safety. The project scope includes the removal of 49,771 square yards of
asphalt pavement, the installation of new asphalt, concrete curb & gutter, sidewalk, utility
relocation/adjustments as needed and driveway tie-ins. All improvements will be constructed within the
existing road prism.
Golden Eagle Impoundment Area Improvements Phase II: Multi-Year
The final phase of this project will design and construct drainage improvements, including modification of trash
racks on Golden Eagle dam inlets. Construction commenced on Phase I in FY25 on phase I and nominal funds are
being requested to finish the project in FY26
The Town is also the recipient of grant funding through the Small Projects Assistance Program of the Flood
Control District of Maricopa County (FCDMC). This grant funding will be applied to the portion of the project that
will improve the protection of the Golden Eagle Dam and the downstream residences, which will occur in FY26.
The FCDMC will fund 75% of the design and construction cost, up to $500,000, through June 30, 2026. The
FCDMC estimated cost share for dam improvements is $90,750, with the Town match of $30,250, and is subject
to change, maintaining the 75% / 25% FCDMC/Town proportional match. The additional $179,000 of requested
Capital Projects funds are for final contingency construction costs that may arise to complete the Impoundment
project already started in the previous fiscal year.
Pedestrian Marked Crosswalks - Town-wide: Multi-Year
This project designs and constructs pedestrian crosswalks and associated signage where appropriate town-wide.
In addition to the crosswalk striping, ADA-compliant curb ramps and refuge islands are constructed where
suitable.
Crosswalks in the Downtown area of Town will be the highest priority, followed by arterials, collectors and local
roads.
Proposed crosswalks in FY26 and beyond include the design and/or construction of:
El Lago Mid-Block Crossing between Saguaro Blvd & La Montana Dr
Avenue of the Fountains & Keith McMahon Dr
Palisades Blvd & Westby Dr
Golden Eagle Blvd & Brittlebush Dr
Palisades Blvd & Sunflower Dr
La Montana Dr & Cambria Dr
La Montana & Hamilton Dr
Guardrail Replacement Town-wide: Multi Year
The Town owns and maintains 10,000 linear feet of guardrail. Due to Federal guidelines changing in 2014,
several segments of pre-and post-incorporation guardrail are no longer in compliance with Federal highway
standards. In 2022, an assessment of the Town's guardrails was performed, and this project will follow the
recommendations of that assessment.
Shea Boulevard Widening - Eastbound from Palisades Blvd to Fountain Hills Blvd - Development Fees/MAG
This project will design and construct the first phase of the expansion of Shea Boulevard. This segment will
complete eastbound Shea, between Palisades Blvd and Fountain Hills Blvd. The ultimate build-out, when
completed, will widen Shea Boulevard to six lanes. The future segments of the project (Project S7001) will widen
Shea Boulevard between Fountain Hills Boulevard and Technology Drive.
Community Center Renovations: Multi- Year
During the initial phase of renovations to the Community Center in 2021, drainage issues were discovered on the
exterior walls and doors of the building. Subsequently, during the Summer of 2022, the building experienced
interior odors, carpet staining, ceiling leaks and increased humidity. An evaluation of the Community Center
structure was performed, and moisture and air testing was completed throughout the building, to determine the
extent of the moisture intrusion damage. The evaluation provided short-term, medium-term and long-term
recommendations. Wet seals were applied to the storefront windows. In FY26, the next phase of work will
follow the recommendations of the consulting engineers, after approval by Town Council.
Town Hall Campus Buildings - Roof Design: Multi-Year
On February 24, 2025, the Town's Consultant completed a comprehensive roof assessment for the Town Hall,
Community Center, Library/Museum, and Central Plant buildings. The evaluation identified significant issues with
the existing low-sloped polyurethane foam roofing systems, including widespread blistering, cracking, and failed
coatings. Additionally, electrical penetrations were found to lack proper flashing jacks, contributing to potential
water intrusion. Debris buildup at roof drains further exacerbates drainage inefficiencies, while deteriorated line
set insulation presents additional vulnerabilities.
To address these concerns, this project will develop signed and sealed construction drawings and specifications
for new roof systems that ensure long-term protection. The design will incorporate necessary repairs, including
a complete roof coating system replacement, proper flashing installation at penetrations, and improved
drainage solutions. By implementing these upgrades, the Town will enhance the structural integrity of its
facilities and prevent future maintenance costs associated with water damage and roofing failures.
Sidewalk Infill and Design: Mulit-Year
This project provides design and construction for ADA-compliant concrete sidewalks and curb ramps where gaps
currently exist. The new sidewalks will provide connectivity to improve the walkability in the Town, and supports
the Town’s Active Transportation Plan and the 2021 Strategic Plan for creating a walkable community.
In recent years, this project constructed infill sidewalks and/or ADA-compliant ramps at the following locations:
Town-Wide Storm Water Infrastructure Rehabilitation: Multi-Year
This project will construct Town-wide stormwater infrastructure maintenance and repair, including pipe
cleaning, inspection, maintenance and treatment, and installation of pipe linings. The Town is responsible for
the maintenance and repair of a large number of drainage structures, including pipe culverts (corrugated metal
and concrete pipe), catch basins, drop inlets and curb openings at drainage parcels. This Project will provide
maintenance and repairs to the Town’s drainage structures. These drainage structures and pipe culverts are
essential components of the Town’s storm drain network. They convey large amounts of runoff to our washes,
thereby mitigating flooding concerns. Many of these large pipe culverts were installed by the County
pre-incorporation. Some drainage structures are over 40 years old.
Dam Sediment Removal and Improvements: Multi-Year
This multi-year program aims to enhance the structural integrity and operational efficiency of the Town's ten
jurisdictional dams, consisting of:
Hesperus Dam
Aspen Dam
North Heights Dam
Golden Eagle Park Dam
Sunridge Canyon Dam
Fountain Lake Dam
Thunder Ridge Dam
Crystal Ridge Dam
Stoneridge Dam
Botanical Garden Dam
The project encompasses the following key components:
Structural Repairs: The inlet and outlet structures of the dams are critical for regulating water flow and
ensuring safety. The project will assess and repair any damage or wear in these structures, addressing
issues such as erosion, concrete degradation, and mechanical failures.
Sediment Removal: Over time, sediment accumulation can impair dam functionality and reduce water
storage capacity. This project will involve the systematic removal of accumulated sediment from each of
the dams, restoring their original capacity and ensuring optimal performance.
Downtown Streetscape Improvement Program
The Downtown Streetscape Improvement Program includes the design and construction of enhancements to
the East and West halves of the Avenue of the Fountains, Verde River Drive, and Parkview Avenue. Spanning five
years, this Capital Program aligns with the Town Council-approved Downtown Strategy (approved in September
2024) to revitalize the Downtown area by improving pedestrian access, esthetics, and overall functionality.
Improvements may include:
widening sidewalks along the Avenue to accommodate outdoor cafe seating
installing new sidewalk along Verde River Drive and Parkview Avenue
installing shade trees, new streetlights, pedestrian lights and hanging aesthetic lights
Fiscal Impact
Fiscal Impact:$11.7MIL
Fiscal Impact:$11.7MIL
Budget Reference:FY26
Funding Source:Capital Projects Fund, Streets, Development Fees
If Multiple Funds utilized, list here:N/A
Budgeted: if No, attach Budget Adjustment Form:N/A
Attachments
FY26 CIP Presentation
Form Review
Inbox Reviewed By Date
Public Works Director (Originator)Justin Weldy 03/11/2025 05:04 PM
Town Attorney Aaron D. Arnson 03/11/2025 04:17 PM
Town Manager Rachael Goodwin 03/20/2025 05:05 PM
Form Started By: Justin Weldy Started On: 03/10/2025 08:36 AM
Final Approval Date: 03/20/2025
Presented by
Kevin Snipes, Community Services Director
Justin T. Weldy, Public Works Director
CIP Council Meeting
March 25, 2025
FY26 Capital Projects Overview
Today’s presentation will cover the following:
Community Services Capital Projects
•FY26
•5-Year Horizon
Public Works Capital Projects
•FY26
•5-Year Horizon
2
Community Services
FY 2026
Proposed Capital Projects
3
Centennial Pavilion Shade Lighting
•CIP Funded
•$50,000
•Dark Sky Compliant lighting
4
Centennial Pavilion Shade Lighting
5
Avenue of the Fountains Park Improvements (Multi-Year)
•CIP Funded
•Year 2 of 3
•$200,000
•Shade
•Color Fountain Lighting
•Event Receptacles
•Landscaping
6
Avenue of the Fountains Park Improvements
7
Desert Vista Pump Enclosure(Multi-Year)
CIP Funded
FY26 - $50,000
FY27 - $300,000
Protection for irrigation pump and electrical from water and sun damage
8
•CIP Funded
•$50,000
•Signage improvement
•Dead Tree Removal and Planting
•Resod High Traffic Areas
•Splash Pad Renovation
Desert Vista/Dog Park Renovation
9
CIP Funded
$50,000
Business and Event Promoter Requested
Fountain Park Splash Pad Shade Electrical and Lighting
10
Fountain Park Ramadas(Multi-Year)
CIP Funded - Replace Five
22Yr/old Ramadas
FY26 - $320,000 (Repl. 3)
FY27 - $200,000 (Repl. 2)11
Fountain Park Panorama Hillside Erosion Control
CIP Funded
$75,000
Decrease slope
Install lighting along sidewalk
12
Four Peaks Electrical Building(Multi-Year)
CIP Funded
FY26 - $50,000
FY27 - $200,000
13
Pleasantville Park
Development Fee Funded
$700,000
Construction
14
Golden Eagle Park Playground Replacement – Multi-Year
$50,000
In Design
15
CIP Funded
FY25 - $150k budget
FY26 - $50k carryover requested
Community Services CIP Summary
Capital Projects FY26
Centennial Pavillion Shade Lighting $ 50,000
Avenue of the Fountains Park Improvements (Multi Year)200,000
Desert Vista Pump Enclosure (Multi-Year)50,000
Desert Vista / Dog Park Renovation 50,000
Fountain Park Splash Pad Shade Electrical and Lighting 50,000
Fountain Park Ramadas (Multi-Year)320,000
Fountain Park Panorama Hillside Erosion Control 75,000
Four Peaks Electrical Building (Multi-Year)50,000
Golden Eagle Playground Equipment Carryover (Multi-Year)50,000
Total FY26 Community Services CIP $895,000
16
Alternate Funded Projects FY26
Pleasantville Park (Development Fees)(Multi-Year)$700,000
Total FY26 Community Services CIP – Alternative Funded Projects $700,000
Community Services CIP Summary – 5-Year Horizon
Description FY27 FY28 FY29 FY30 FY31
Avenue Linear Park Improvements $200,000
Desert Vista Pump Enclosure 300,000
Fountain Park Ramadas 200,000
Four Peaks Electrical Building 200,000
Lake Liner Replacement (Planning/Design/Install)$1,000,000 $3,000,000 $3,000,000 $10,000,000
Park Improvements (Golden Eagle Park)200,000 200,000 200,000
Park Improvements (Desert Vista Playground
Replacement)
$400,000
Total Community Services CIP $900,000 $1,200,000 $3,200,000 $3,200,000 $10,400,000
17
Public Works
FY 2026
Proposed Capital Projects
18
S7003 – Palomino Boulevard Reconstruction
CIP Funded, to be reimbursed
by STREETS Funds
Palomino Blvd
(Palisades Blvd to Fountain
Hills Blvd)
FY26 - $5,400,000
S7003 – Palomino Boulevard ReconstructionConstruction - $5.4M
CIP Funded, to be reimbursed by
STREETS Funds
Palomino Blvd
(Palisades Blvd to Fountain Hills Blvd)
Existing Conditions:
9’ Shoulders
15’ Travel Lanes
12’ Center Turn Lane
Existing Condition
Intermediate Condition
21
Future Condition with Sidewalk
5’ POTENTIAL FUTURE Sidewalks
7½’ Shoulders
11’ Travel Lanes
12’ Center Turn Lane
S7003 – Palomino Boulevard ReconstructionConstruction - $5.4M
22
Golden Eagle Impoundment Area Improvements
(Multi-Year)
CIP / Grant Funded
Construction Underway
FY26 - Contingency - $179k
FY26 – Dam Improvements
FCDMC Grant - $90,750
Town Match - $30,250
Total Requested for FY26
$300k
Pedestrian Marked Crosswalks – Town -Wide
$150,000 (Multi-Year)
23
Proposed Marked Crosswalk Locations:
•El Lago (Mid-block)
•Golden Eagle & Brittlebush
•Palisades & Sunflower
•La Montana & Cambria
•La Montana & Hamilton
S6068 – Town wide Guardrail replacement
$50,000 CIP (Multi-Year)
CIP Funded
24
FY26 - $50k
FY27–FY30 - $50k/Year
25
S6058 – Shea Boulevard Widening
South Side Between Palisades Blvd & FHBLVD
State Funding (Prop 400) (Development Fee Eligible)
CIP / Grant / Development Fee
Funded
Total Construction Cost - $3M
State Share - $2.1M
Development Fees - $800k
CIP - $100k
F4037 Community Center Renovations
$300,000
26
CIP Funded
FY26
Construction - $300k
Town Hall Campus Buildings - Roof Design
$125,000
27
CIP Funded
FY26
Design - $125k
S6061 Sidewalk Infill and Design
Design/Construction $325,000 (Multi-Year)
28
CIP Funded
FY26
Design - $100k
Construction - $225k
FY27-30 - $325k/year
D6060 Town Wide Storm Water Infrastructure Rehabilitation
$150,000 (Multi-Year)
29
CIP Funded
FY26 - $150k
FY27-30 - $150k/year
30
D6068 - Dam Sediment Removal and Improvements
$100,000 (Multi-Year)
CIP Funded
FY26 - $100k
FY27-30 - $100k/year
For Structural Repairs and
Sediment Removal at the
Town’s Ten Jurisdictional
Dams
CIP Funded
•Multi-Year Project to design and install Infrastructure Improvements as part of the Council-Approved Downtown Strategy
•Four Phases are proposed for completion over a 5-year period
•Eastern Half of The Avenue (Verde River to Saguaro)
•Western Half of The Avenue (La Montana to Verde River)
•Verde River Drive
•Parkview Avenue
31
E8506 – Downtown Streetscape Improvement Program
$225,000 Design (Multi-Year)
32
Each Phase includes Design and
Construction.
FY26 - Design of the Eastern half
of The Avenue ($225k)
Proposed improvements include
the widening of the sidewalk to
accommodate outdoor cafes,
relocation of street lights,
removal of palm trees and the
installation of shade trees, utility
relocations and new string lights
running parallel to the Avenue
E8506 – Downtown Streetscape Improvement Program
$225,000 Design (Multi-Year)
33
Capital Projects FY26 FY27 FY28 FY29 FY30 Total
Design $225,000 $ 238,000 $ 201,000 $ 314,000 N/A $ 978,000
Construction N/A $2,245,000 $2,372,000 $2,003,000 $3,135,000 $9,755,000
Total:$225,000 $2,483,000 $2,573,000 $2,317,000 $3,135,000 $10,733,000
Design of
East ½ of
Avenue
Const. of East ½
PLUS
Design of West ½
Const. of West ½
PLUS
Design of Verde River
Const. of Verde River
PLUS
Design of Parkview
Construction of
Parkview
Capital Projects Design Cost Construction
Cost
Total Cost
East ½ of Avenue $225,000 $2,245,000 $2,470,000
West ½ of Avenue $238,000 $2,372,000 $2,610,000
Verde River Dr $201,000 $2,003,000 $2,204,000
Parkview Ave $314,000 $3,135,000 $3,449,000
Total:$978,000 $9,755,000 $10,733,000
E8506 – Downtown Streetscape Improvement Program
$225,000 Design (Multi-Year)
Proposed Downtown Improvement 5 YR – Capital Fund
Option 1
Capital Projects FY26 FY27 FY28 FY29 FY30
Streetscapes $225,000 $2,483,000 $2,573,000 $2,317,000 $3,135,000
Total:$225,000 $2,483,000 $2,573,000 $2,317,000 $3,135,000
Streetscape Scope Design of East ½ of Avenue Const. of East ½
PLUS
Design of West ½
Const. of West ½
PLUS
Design of Verde River
Const. of Verde River
PLUS
Design of Parkview
Construction of
Parkview
Proposed Downtown Improvements 5 YR – Capital Fund
Option 2
Capital Projects FY26 FY27 FY28 FY29 FY30
Streetscapes $201,000 $2,317,000 $3,360,000 $2,483,000 $2,372,000
Total:$201,000 $2,317,000 $3,360,000 $2,483,000 $2,372,000
Streetscape Scope Design of Verde River Const. of Verde river
PLUS
Design of Parkview
Const. of Parkview
PLUS
Design of East ½ of Ave
Const. of East ½ of Ave
PLUS
Design of West ½ of
Ave
Construction of
West ½ of Ave
Proposed Downtown Improvements 5 YR – Capital Fund
Option 3
Capital Projects FY26 FY27 FY28 FY29 FY30
Streetscapes $515,000 $2,003,000 $3,360,000 $2,483,000 $2,372,000
Total:$515,000 $2,003,000 $3,360,000 $2,483,000 $2,372,000
Streetscape Scope Design of Verde River and
Parkview
Const. of Verde river Const. of Parkview
PLUS
Design of East ½ of Ave
Const. of East ½ of Ave
PLUS
Design of West ½ of
Ave
Construction of
West ½ of Ave
FY26 Public Works CIP Summary
Capital Projects FY 26
Palomino Boulevard Reconstruction $5,400,000
Pedestrian Marked Crosswalks (Multi-Year)150,000
Town Wide Guardrail Replacement (Multi-Year)50,000
Community Center Renovations 300,000
Town Hall Campus Buildings - Roof Design 125,000
Sidewalk Infill & Design (Multi-Year)325,000
Town Wide Storm Water Infrastructure Rehabilitation (Multi-Year)150,000
Dam Sediment Removal and Improvements (Multi-Year)100,000
Downtown Streetscape Improvement Program (Multi-Year)225,000
Total FY26 Public Works CIP $6,825,000
37
FY26 Public Works CIP Summary – Grant Projects
Grant Funded Projects
FY 26
Initial Town
Expenditure
Grant
Reimbursement
Town Final
Expenditure after
Reimbursement
Golden Eagle Impoundment Area Improvements $300,000 $90,750 $209,250
Shea Boulevard Widening – Palisades to FHBLVD (Prop 400)$ 3,000,000 $ 2,100,000 $ 900,000
Total Public Works Grant Funded FY26 Projects $ 3,300,000 $ 2,190,750 $ 1,109,250
38
Public Works CIP Summary – Outer Years
Capital Projects FY27 FY28 FY29 FY30 FY31
Pedestrian Marked Crosswalks (Multi-Year)$150,000 $150,000 $150,000 $150,000 $150,000
Town Wide Guardrail Replacement (Multi-Year)$50,000 $50,000 $50,000 $50,000 $50,000
Sidewalk Infill & Design (Multi-Year)$325,000 $325,000 $325,000 $325,000 $325,000
Town Wide Storm Water Infrastructure
Rehabilitation (Multi-Year)
$150,000 $150,000 $150,000 $150,000 $150,000
Dam Sediment Removal and Improvements (Multi-
Year)
$100,000 $100,000 $100,000 $100,000 $100,000
Downtown Streetscape Improvements (Multi-Year)$2,483,000 $2,573,000 $2,317,000 $3,135,000
Total Public Works CIP – Outer Years $3,258,000 $3,348,000 $3,092,000 $3,910,000 $775,000
39