RESOLUTION NO. 2003 -18
A RESOLUTION OF THE MAYOR AND COUNCIL OF THE TOWN OF
FOUNTAIN HILLS, ARIZONA, APPROVING AN INTERGOVERNMENTAL
AGREEMENT WITH THE STATE OF ARIZONA FOR THE
CONSTRUCTION OF THE SHEA BOULEVARD BIKE PATH.
BE IT RESOLVED BY THE MAYOR AND COUNCIL OF THE TOWN OF
FOUNTAIN HILLS, ARIZONA as follows:
SECTION 1. That the Intergovernmental Agreement between the Town of Fountain
Hills and the State of Arizona for the construction of the Shea Boulevard Bike Path is hereby
approved in the form attached hereto as Exhibit A and incorporated herein by reference.
SECTION 2. That the Mayor, the Town Manager, the Town Clerk and the Town
Attorney are hereby authorized and directed to take all steps necessary to cause the execution of
the Agreement.
PASSED AND ADOPTED BY the Mayor and Council of the Town of Fountain Hills,
Arizona, May 1, 2003.
FOR THE TOWN OF FOUiWAIN HILLS:
Timothy G. ickering, Town Manager
9196W i\ R,nlmbm \AWTIGA.rtsLU�
M} -0 }I
ATTESTED TO:
APPROVED AS TO FORM:
Andrew J. McGuire, Town Attorney
AG Contract No.. KR03- 0389TRN
ADOT ECS File No JPA 02 -191
Project No.: 0000 CM FTH
TRACS No: SS451 01C
Project: Shea Boulevard Bike Path
INTERGOVERNMENTAL AGREEMENT
BETWEEN
THE STATE OF ARIZONA
AND
THE TOWN OF FOUNTAIN HILLS
THIS AGREEMENT is entered into , 2003, pursuant to
Arizona Revised Statutes, Sections 11 -951 through 11 -954, as amended, between the STATE OF
ARIZONA, acting by and through its DEPARTMENT OF TRANSPORTATION (the "State ") and the
TOWN OF FOUNTAIN HILLS acting by and through its MAYOR and TOWN COUNCIL (the "Town").
I. RECITALS
• 1. The State is empowered by Arizona Revised Statutes Section 28-401 and 28 -334 to enter into
this agreement and has delegated to the undersigned the authority to execute this agreement on behalf of
the State.
2. The Town is empowered by Arizona Revised Statutes Section 48 -572 to enter into this
agreement and has by resolution, a copy of which is attached hereto and made a part hereof, resolved to
enter into this agreement and has authorized the undersigned to execute this agreement on behalf of the
Town.
3. Congress has authorized appropriations for, but not limited to, the construction of streets and
primary, feeder and farm -to- market roads: the replacement of bridges; the elimination of roadside
obstacles; and the application of pavement markings.
4. Such project within the boundary of the Town has been selected by the Town; the field survey of
the project has been completed; and the plans, estimates and specifications have been prepared and, as
required, submitted to the Federal Highway Administration (FHWA) for its approval.
5. The only interest of the State in the project is in the acquisition of federal funds for the use and
benefit of the Town by reason of federal law and regulations under which funds for the project are
authorized to be expended.
9
Page 2 JPA 02 -191
6. The Town, in order to obtain federal funds for the construction of the project, is willing to provide
Town funds to match federal funds in the ratio required or as finally fixed and determined by the Town
and FHWA, including actual construction engineering and administration costs (CE).
7. The work embraced in this agreement is the construction of a bike path, and the estimated costs
are as follows:
Estimated Construction Cost: ........................................................................ $410.250.00
5% Contingency: ..................................................................................... ..... S 20,513.00
Estimated subtotal Construction Cost: .......................................................... $430,763.00
15% Construction Engineering Cost: ............................................................ S 64,614.00
TOTAL ESTIMATED CONSTRUCTION COST: ....................... ................... 5495,377.00
Shared Federal -Aid Safety Funds @ 94.3%: ................... ............................ $440.00000
Shared Town of Fountain Hills Funds @ 5.7%: ............................................ S 26,596.00
Estimated Additional Town of Fountain Hills Funds @ 100%: ...................... $ 28,781.00
Estimated Total Town of Fountain Hills Funds: ............................................ $ 55,377.00
'Includes Construction Engineering at 15% and Change Orders at 5 %.
THEREFORE, in consideration of the mutual covenants expressed herein, it is agreed as follows:
11. SCOPE OF WORK
1. The State shall submit a program containing the aforementioned project to FHWA with the
recommendation that it be approved for construction.
a. If such project is approved for construction by FHWA and the funds are available for
construction, the Town will and does hereby designate the State as authorized agent for the Town. The
State hereby agrees to be authorized agent for the Town, and with the aid and consent of the Town and
the FHWA will proceed to advertise for, receive and open bids, and subject to the concurrence of the
Town and the FHWA, enter into a contract with a firm on behalf of the Town to whom the award is made
for the construction of the project, such project to be performed, completed, accepted and paid for in
accordance with the instructions and requirements of the Town and the Standard Specifications for Road
and Bridge Construction of the Arizona Department of Transportation. The State will enter into a Project
Agreement with FHWA on behalf of the Town covering the work embraced in said construction contract
and will request the maximum federal funds available, including construction engineering and
administration costs. Should costs exceed the maximum federal funds available, it is understood and
agreed that the Town will be responsible for any overage.
b. Should unforeseen conditions or circumstances increase the cost of said work required by a
change in the extent or scope of the work called for in this agreement, the Town shall be obligated to
incur and will pay for said increased costs.
2. Prior to the solicitation of bids, the Town shall deposit funds with the State in the amount
determined to be necessary to match federal funds in the ratio required.
3. The Town shall acquire the necessary right -of -way and hereby certifies that all necessary rights -
of -way have been or will be acquired prior to advertisement for bid.
4. The Town shall remove from the proposed right -of -way all obstructions or unauthorized
encroachments of whatever nature, either above or below the surface of the roadway, and hereby
Page 3 JPA 02 -191
certifies that all obstructions and encroachments have been or will be removed there from, prior to the
start of construction.
5. The Town shall not permit or allow any encroachments, except those authorized by permit, upon,
or private use of, the right of way. In the event of any unauthorized encroachment or improper use, the
Town shall take all necessary steps to remove or prevent any such encroachment or use.
6. Upon completion of construction, the Town shall provide for, at its own costs and as an annual
item in its budget, proper maintenance will be provided, all in accordance with the requirements of the
current edition of the Manual on Uniform Traffic Control Devises for Streets and Highways.
111. MISCELLANEOUS PROVISIONS
1. The State assumes no financial obligation or liability under this agreement. The Town assumes
full responsibility for the design, plans and specifications, reports, the engineering in connection therewith,
and the construction of the improvements contemplated, cost over -runs and construction claims. It is
understood and agreed that the State's participation is confined solely to securing federal aid; that any
damages arising from carrying out, in any respect, the terms of this agreement or any modification
thereof, shall be solely the liability of the Town and that the Town hereby agrees to save and hold
harmless and indemnify from loss the State, any of its departments, agencies, officers or employees from
any and all cost and/or damage incurred by any of the above and from any other damage to any person
or property whatsoever, which is caused by any activity, condition, or event arising out of the performance
or nonperformance of any provisions of this agreement by the State, any of its departments, agencies,
officers and employees, the Town, any of its agents, officers and employees, or any of its independent
contractors. Costs incurred by the State, any of its departments, agencies, officers or employees shall
include in the event of any action, court costs, and expenses of litigation or attorneys' fees.
2. The cost of the design, construction and construction engineering work covered by this
agreement is to be borne by FHWA and Town, each in the proportion prescribed or as fixed and
determined by the FHWA as stipulated in this agreement. Therefore, Town agrees to furnish and provide
the difference between the total cost of the work provided for in this agreement and the amount of federal
aid received.
3. This agreement shall remain in force and effect until completion of the work; provided, however,
that any provisions in this agreement for maintenance shall be perpetual, unless assumed by another
entity.
4. This agreement shall become effective upon filing with the Secretary of State.
5. This agreement may be cancelled in accordance with Arizona Revised Statutes Section 38 -511.
6. The provisions of Arizona Revised Statutes Section 35 -214 are applicable to this contract.
7. In the event of any controversy, which may arise out of this agreement, the parties hereto agree
to abide by required arbitration as is set forth for public works contracts in Arizona Revised
Statutes Section 12 -1518.
8. All notices or demands upon any party to this agreement shall be in writing and shall be delivered
in person or sent by mail addressed as follows:
Page 4
Arizona Department of Transportation
Joint Project Administration
205 S. 17th Avenue — Mail Drop 616E
Phoenix, AZ 85007
FAX (602- 712 -7424
JPA 02 -191
Town of Fountain Hills
Town Manager
16836 East Palisades Boulevard,
Fountain Hills, AZ 85269
9. Attached hereto and incorporated herein is the written determination of each party's legal counsel
that the parties are authorized under the laws of this state to enter into this agreement and that the
agreement is in proper form.
IN WITNESS WHEREOF, the parties have executed this agreement the day and year first above written.
TOWN OF FOUNTAIN HILLS
By
BEVELYN.l�bENDER
Town Clerk
02- 191ENVIR- Fountain Hills- Enhncmnt
17Mar 2003 - ly
STATE OF ARIZONA
Department of Transportation
By
SUSAN TELLEZ
Contract Administrator
JPA 02 -191
APPROVAL OF THE TOWN OF FOUNTAIN HILLS ATTORNEY
I have reviewed the above referenced proposed intergovernmental agreement,
between the STATE OF ARIZONA, acting by and through its DEPARTMENT OF
TRANSPORTATION (the "State ") and FOUNTAIN HILLS, declare this agreement to in proper form
and within the powers and authority granted to the Town under the laws of the State of Arizona.
No opinion is expressed as to the authority of the State to enter into this agreement.
DATED this day of 1 `4ki 2003.
AT�
Attorney